The steel is the cheap part. Here is the whole RSJ job priced line by line, at typical 2026 quotes, and where not to economise.
Question 1
What is the clear span of the opening, in metres?
Measure the structural opening. The beam itself will be longer, because it has to bear on masonry at each end; how much bearing, and on what padstone, comes out of the calcs rather than a rule of thumb. Between sizes? Round up.
Email me this result
We will send you these figures and a link back to them. One email, nothing else unless you tick the box.
RSJ installation cost, line by line
| Line | Typical 2026 cost |
|---|---|
| Steel beam supplied (small domestic sections) | £150–£300 |
| Structural engineer's calcs | £250–£500 |
| Builder installation: props, padstones, fitting, making good | £1,000–£2,000 |
| Building control application (set by each council, no national scale) | £200–£400 on the 2026 council scales we checked |
| Typical all-in total | £1,600–£3,200 |
Steel beam prices per metre
Steel is sold by the metre for each section size, and few stockists publish a price. F H Brundle lists a 178x102x19 universal beam at £35.10 a metre and a 254x102x25 at £46.20 a metre. Both are S355, read on its own product pages on 12 October 2026.
No stockist we read prices the heavier 203 UC, 254x146 and 305 series sections that longer or heavier openings usually need, so treat those as quote-only. Figures, sources and silent stockists are in our UK steel beam cost index.
What moves the price
- Beam size and weight: a 3 m beam in the light UC range sits at the bottom of the supplied band; long or heavy UBs cost more to buy and much more to handle, sometimes needing lifting kit.
- Access: a beam walked through a front door prices differently from one craned over a roof.
- Temporary works: propping two floors while a wall comes out is real labour, and it is where cheap quotes cut corners.
- Making good: plastering, flooring and decorating around the new steel often costs as much as fitting it.
Where not to save
The calcs and the sign-off. Skipping the engineer for a span table or a free online calculator saves a few hundred pounds and costs it back with interest:
- building control has to be satisfied the beam meets Part A, and in practice will not take a bare span table;
- an oversized 'safe guess' beam wastes steel and headroom;
- a missing completion certificate resurfaces at sale, when the buyer's conveyancer asks, and the fix is a retrospective regularisation application with opening-up works.
All figures here are typical 2026 quotes and vary by region and job. Treat them as a sanity check on real quotes.
Start with the checker for the indicative range, then have an engineer run the real numbers. That order keeps the total at the bottom of the band.